Further to the answer to question S6W-35302 by Gillian Martin on 12 March 2025, when the leasing agreement between the developers of the In…

Answered Asked by Mercedes Villalba Lab Lodged 6 May 2025

The question

To ask the Scottish Government, further to the answer to question S6W-35302 by Gillian Martin on 12 March 2025, when the leasing agreement between the developers of the Inch Cape Offshore Wind Farm site and Crown Estate Scotland was signed.

The answer

Answered by Gillian Martin on 21 May 2025 · 15 days after it was lodged, on time

The Lease for the Inch Cape Offshore windfarm was signed on 24 January 2025.