Written Question · S6W-34928 · Session 6
For what reason the assessment process for the Borderlands Solway Coast and Marine Project bid has been delayed, and by what date a decisio…
The question
To ask the Scottish Government for what reason the assessment process for the Borderlands Solway Coast and Marine Project bid has been delayed, and by what date a decision will be made on the funding application.
The answer
The Solway Cost and Marine Pilot Project (SCAMPP), business justification case was assessed by the Scottish and UK Governments using HM Treasury Green Book guidance. Appropriate due diligence was undertaken and, following further work by the project development partners to clearly articulate its economic and environmental benefits and demonstrate value for money, it was endorsed by Scottish and UK Government on 20 February 2025. This will allow the research element to proceed.
In the Official Report
No contribution in the Official Report cites S6W-34928 by reference.