Written Question · S6W-34047 · Session 6
Further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, what the expected (a) timeline and (b) costs are for comple…
The question
To ask the Scottish Government, further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, what the expected (a) timeline and (b) costs are for completing ongoing repairs to the A90 Finavon Bridge, which was damaged during Storm Babet.
The answer
The current estimated costs are £716,432.40. However, this may increase as the investigation and design for the permanent works progresses.Construction is anticipated to be complete by the end of September 2025. However, investigations and permanent works design are still ongoing. Ecological factors at the site will also severely affect the available construction window