Further to the answer to question S6W-31715 by Alasdair Allan on 9 December 2024, what the total size of the Scottish Industrial Energy Tra…

Answered Asked by Daniel Johnson Lab Lodged 10 Dec 2024

The question

To ask the Scottish Government, further to the answer to question S6W-31715 by Alasdair Allan on 9 December 2024, what the total size of the Scottish Industrial Energy Transformation Fund is, and whether the additional funding received as a result of the UK Government's £185 million investment has been incorporated into the fund.

The answer

Answered by Alasdair Allan on 6 Jan 2025 · 27 days after it was lodged, on time

The total size of the Scottish Industrial Energy Transformation Fund is £34 million. The UK government budget committed funding from which Barnett consequentials will be received, however, these are accrued to the Scottish Government as a whole and it is for Scottish Ministers to decide how they should be allocated based on their priorities.