When work will begin on developing a just transition plan for Mossmorran.

Answered Asked by Michael Matheson SNP Lodged 14 Nov 2024

The question

To ask the Scottish Government when work will begin on developing a just transition plan for Mossmorran.

The answer

Answered by Gillian Martin on 27 Nov 2024 · 13 days after it was lodged, on time

The Scottish Government has committed to the development of a just transition plan for Mossmorran following completion of the just transition plan for Grangemouth in 2025. As with the Grangemouth just transition plan, this work will be co-designed with key stakeholders including industry, the workforce and the community. The Scottish Government is actively engaging with relevant stakeholders as part of the scoping phase of this programme of work.

In the Official Report

No contribution in the Official Report cites S6W-31333 by reference.