Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S6W-31127 · Session 6

Further to the answer to question S6W-29945 by Ivan McKee on 24 September 2024, for what reason it did not make provision for community ene…

Answered Asked by Sarah Boyack Lab Lodged 7 Nov 2024

The question

To ask the Scottish Government, further to the answer to question S6W-29945 by Ivan McKee on 24 September 2024, for what reason it did not make provision for community energy suppliers to be added to the generation mix in the contract awarded to EDF, in light of its support for community wealth building, and how the policy approach adopted supports community wealth building.

The answer

Answered by Ivan McKee on 18 Nov 2024 · 11 days after it was lodged, on time

The national electricity framework covers circa 300 organisations across Scotland, covering all sectors – Local Government, Central Government, NHS, Universities and colleges. Any energy supplier needs to have the capacity to supply and service all organisations by providing the ability to pre-purchase electricity and also provide a billing service.The mix of energy used is the suppliers decision, the energy mix cannot be decided by Scottish Procurement.The community energy element was not raised as a requirement in the scoping of the procurement strategy which is developed by the framework users, who are representatives from across the public sector.

In the Official Report