Written Question · S6W-30093 · Session 6
When the junction improvements on the A75 at Haugh of Urr will be completed.
The question
To ask the Scottish Government when the junction improvements on the A75 at Haugh of Urr will be completed.
The answer
The Scottish Government, through Transport Scotland’s Trunk Road Casualty Reduction programme of works, is delivering improvements at the A75 Haugh of Urr junction. Construction of static sign improvements, relating to advanced direction signage and rationalisation of existing signage, is currently programmed for November 2024. An electronic vehicle-activated sign system to warn drivers of vehicles turning or waiting to turn at the junction is also proposed at the junction. This may be delivered this financial year subject to the approval of a non-prescribed sign application.
In the Official Report
No contribution in the Official Report cites S6W-30093 by reference.