Written Question · S6W-30029 · Session 6
Which of the 42 prioritised flood protection schemes that were planned between 2016 and 2021 have yet to be completed, and when the expecte…
The question
To ask the Scottish Government which of the 42 prioritised flood protection schemes that were planned between 2016 and 2021 have yet to be completed, and when the expected completion date is for each.
The answer
The responsibility for development and delivery of flood protection schemes rests with individual local authorities, who are best placed to respond to local resilience needs.The Scottish Government provides funding to local authorities to enable delivery of these important projects. £570million will be invested in flood resilience in the period 2016-2026. 40 of 42 have received funding to support development. 2 are not eligible because they have previously received funding.15 of the cycle 1 flood schemes have now been completed. The status of those that remain is as follows:Scheme nameLocal authorityCurrent stageEst. completionMillport CoastalNorth AyrshireUnder construction2024CampbeltownArgyll and ButeUnder construction2024HawickBordersUnder construction2024StranraerDumfries and GallowayUnder construction2024Upper GarnockNorth AyrshireUnder construction2024MilnathortPerth and KinrossConstruction due to start 2025 Mill Burn MillportNorth AyrshireConstruction due to start 2025 Kilmacolm – Glenmosston BurnInverclydeLegal confirmation complete ComriePerth and KinrossLegal confirmation complete Dumfries
- WhitesandsDumfries and GallowayLegal confirmation complete Quarriers VillageInverclydeLegal confirmation complete Dumbarton Gruggies BurnWest DunbartonshireLegal notification complete South KinrossPerth and KinrossLegal notification complete MusselburghEast LothianLegal notification complete Bridge of AllanStirlingLegal notification complete Newton Stewart/ River CreeDumfries and GallowayLegal notification complete Grangemouth FPSFalkirkLegal notification complete St Andrews
- Kinness BurnFifeWithdrawn – notification deadline missed South FordsComhairle nan Eilean SiarWithdrawn – notification deadline missed SconePerth and KinrossWithdrawn – notification deadline missed HaddingtonEast LothianWithdrawn – notification deadline missed CallanderStirlingWithdrawn – notification deadline missed StirlingStirlingWithdrawn – notification deadline missed LangholmDumfries and GallowayWithdrawn Greenock CoveInverclydeScheme no longer required
- WhitesandsDumfries and GallowayLegal confirmation complete Quarriers VillageInverclydeLegal confirmation complete Dumbarton Gruggies BurnWest DunbartonshireLegal notification complete South KinrossPerth and KinrossLegal notification complete MusselburghEast LothianLegal notification complete Bridge of AllanStirlingLegal notification complete Newton Stewart/ River CreeDumfries and GallowayLegal notification complete Grangemouth FPSFalkirkLegal notification complete St Andrews
- Kinness BurnFifeWithdrawn – notification deadline missed South FordsComhairle nan Eilean SiarWithdrawn – notification deadline missed SconePerth and KinrossWithdrawn – notification deadline missed HaddingtonEast LothianWithdrawn – notification deadline missed CallanderStirlingWithdrawn – notification deadline missed StirlingStirlingWithdrawn – notification deadline missed LangholmDumfries and GallowayWithdrawn Greenock CoveInverclydeScheme no longer required