Further to the answer to question S6W-29523 by Alasdair Allan on 16 September 2024, how it accurately monitors the total installed solar ca…

Answered Asked by Maurice Golden Con Lodged 17 Sep 2024

The question

To ask the Scottish Government, further to the answer to question S6W-29523 by Alasdair Allan on 16 September 2024, how it accurately monitors the total installed solar capacity, of all types, approved by local authorities.

The answer

Answered by Alasdair Allan on 1 Oct 2024 · 14 days after it was lodged, on time

The approval, construction and installation of Solar photovoltaic projects over 150kW is monitored through the Renewable Energy Planning Database (REPD). Information is provided both as a spreadsheet and as an interactive map which provides the location and capacity of all renewable energy projects within the planning system.Renewable Energy Planning Database | DESNZ & Barbour ABI (barbour-abi.com)The electricity capacity and generation provided by all grid-connected renewable projects is monitored through UK Renewables Energy Trends.Energy Trends: UK renewables
- GOV.UK (www.gov.uk)Both these data sources are updated on a quarterly basis and summary data is provided within Scotland's quarterly energy statistics publication.Quarterly energy statistics Scotland
- gov.scot (www.gov.scot)Details of all small-scale renewable energy installations in the UK are available from the MCS data dashboardAbout the MCS Data Dashboard
- MCS (mcscertified.com)