Written Question · S6W-29827 · Session 6

Whether it will provide an update on the number of properties still to be connected under the R100 Central contract.

Answered Asked by Stephen Kerr Con Lodged 11 Sep 2024

The question

To ask the Scottish Government whether it will provide an update on the number of properties still to be connected under the R100 Central contract.

The answer

Answered by Richard Lochhead on 19 Sep 2024 · 8 days after it was lodged, on time

Latest assured figure (from 31 July 2024) showed that around 14,000 premises were still expected to be connected through the R100 Central contract.Latest coverage figures, including premises connected that were beyond the scope of the initial R100 contracts, are available on our website at Data insights | Digital Scotland Superfast Broadband.

In the Official Report

No contribution in the Official Report cites S6W-29827 by reference.