To ask the Scottish Government how much of the £250 million 10-year Peatland ACTION funding package that has been committed for peatland restoration remains to be spent in the remainder of the delivery period, and how much it expects to spend in each of the remaining years.
The answer
The spend on peatland restoration in recent years is shown in the following table:YearSpend (£m)2020-218.02021-2214.62022-2317.32023-2427.9Total:67.8Budget allocations are considered each year as part of the Scottish budget process.
In the Official Report