Whether investment in the (a) medium- and (b) long-term replacements for the A83 Rest and Be Thankful will be impacted by the reported anno…
The question
To ask the Scottish Government whether investment in the (a) medium- and (b) long-term replacements for the A83 Rest and Be Thankful will be impacted by the reported announcement that the Cabinet Secretary for Finance and Local Government has imposed emergency spending controls.
The answer
The Scottish Government remains committed to delivering medium and long term solutions to address landslip risks at the A83 Rest and Be Thankful.Delivery of a permanent and resilient solution is a priority and we continue to seek ways to achieve that as quickly as possible. Following identification of a preferred option last year, the next step for the permanent solution, which is the detailed development and assessment of the preferred option, is progressing at pace and will conclude with the publication of draft Orders for comment, currently expected by the end of this year. As with all infrastructure projects, delivery of the scheme can only commence if approved under the relevant statutory authorisation procedures and thereafter a timetable for construction can be set.At the same time, improvements to the existing Old Military Road (OMR) through the Glen Croe corridor are being made to make it a more resilient diversion route until the long term solution is in place.Funding is included in the 2024-25 Budget to continue to deliver the medium term solution and progress the essential preparatory work on the long term solution.Funding to construct the long term solution to the landslip risks will be determined annually as part of the annual Scottish Budget setting exercises. However, this scheme is a priority for the Scottish Government, noting it is a key recommendation in the second Strategic Transport Projects Review (STPR2).
In the Official Report
No contribution in the Official Report cites S6W-29197 by reference.