For what reason additional grid capacity and infrastructure at Bearholm substation has reportedly been granted planning permission, in ligh…

Answered Asked by Oliver Mundell Con Lodged 24 Jul 2024

The question

To ask the Scottish Government for what reason additional grid capacity and infrastructure at Bearholm substation has reportedly been granted planning permission, in light of the Rivox and Scoop Hill Windfarm planning applications reportedly having not yet been determined.

The answer

Answered by Ivan McKee on 7 Aug 2024 · 14 days after it was lodged, on time

The decision to grant planning permission for an extension to an existing substation at Bearholm near Moffat was made by the relevant planning authority, Dumfries and Galloway Council.
Planning authorities are required to determine any valid application submitted to them in accordance with the relevant local development plan and National Planning Framework 4 (NPF4) unless there are material considerations which justify a departure from the plan. The decision notice of the authority is required to include the reasons for the decision. In addition, as part of the decision-making process the authority is required to produce a report setting out their consideration of the application and the material considerations taken into account. The decision notice and report are published on the planning authority’s website.
Applications for consent for the Rivox Wind Energy Hub and Scoop Hill Community Wind Farm projects are currently with the Scottish Ministers for determination under section 36 of the Electricity Act 1989.