Written Question · S6W-28585 · Session 6
Further to the answer to question S6W-28234 by Gillian Martin on 5 July 2024, whether it will provide the information requested regarding f…
The question
To ask the Scottish Government, further to the answer to question S6W-28234 by Gillian Martin on 5 July 2024, whether it will provide the information requested regarding for what reason the timeframe for the (a) Nitrogen Impacts on the Natural Environment (NINE) project and (b) assessment of potential costs for implementing site conditioning monitoring improvements has been extended beyond 2024 to 2026 instead of providing revised completion dates.
The answer
Cleaner Air for Scotland 2 (CAFS2) was published in July 2021 with two actions on the topic of nitrogen deposition. At the time of publication these actions were assigned a medium term timescale for delivery by 2024.
In April 2022 the Nitrogen Impacts on the Natural Environment (NINE) project led by the James Hutton Institute commenced as part of the Strategic Research Programme for air quality. In considering how to take the CAFS2 actions forward, Scottish Government worked with the NINE project team to ensure it would deliver the CAFS2 evidence needs. Following commencement of the NINE project we revised the delivery milestones for the CASF2 actions to align with the project deliverables.
The NINE project was commissioned on time and continues to be on track for delivery by 2027, with CAFS2 elements to be delivered in 2026.
In April 2022 the Nitrogen Impacts on the Natural Environment (NINE) project led by the James Hutton Institute commenced as part of the Strategic Research Programme for air quality. In considering how to take the CAFS2 actions forward, Scottish Government worked with the NINE project team to ensure it would deliver the CAFS2 evidence needs. Following commencement of the NINE project we revised the delivery milestones for the CASF2 actions to align with the project deliverables.
The NINE project was commissioned on time and continues to be on track for delivery by 2027, with CAFS2 elements to be delivered in 2026.
In the Official Report
No contribution in the Official Report cites S6W-28585 by reference.