Whether it has any plans to re-examine the installation of a fixed link between the Cowal and Kintyre, as originally proposed in the option…
The question
To ask the Scottish Government whether it has any plans to re-examine the installation of a fixed link between the Cowal and Kintyre, as originally proposed in the option appraisal for the second Strategic Transport Projects Review (STPR2).
The answer
STPR2 (Recommendation 41) recommends that further study work to better understand the benefits, costs and challenges associated with a Sound of Harris fixed link, a Sound of Barra fixed link and a fixed link between Mull and the Scottish mainland is undertaken.
There are currently no plans to revisit any of the fixed link options that did not make it to final consideration during the STPR2 appraisal process. The reason why a particular option did not progress can be found in Appendix G of the Final Technical Report .
There are currently no plans to revisit any of the fixed link options that did not make it to final consideration during the STPR2 appraisal process. The reason why a particular option did not progress can be found in Appendix G of the Final Technical Report .