Whether any repair work has been required on the 16 R100 subsea cables to Scottish islands, broken down by (a) year and (b) cost of repair.

Answered Asked by Tim Eagle Con Lodged 9 May 2024

The question

To ask the Scottish Government whether any repair work has been required on the 16 R100 subsea cables to Scottish islands, broken down by (a) year and (b) cost of repair.

The answer

Answered by Tom Arthur on 28 May 2024 · 19 days after it was lodged, on time

The BT Subsea Team has confirmed that there have been no recorded faults or repairs required to the R100 subsea cables to Scottish islands since deployment in 2022.