Whether it will provide an update on the total cost of any financial penalties issued by Transport Scotland to CalMac Ferries since October…

Answered Asked by Tim Eagle Con Lodged 7 May 2024

The question

To ask the Scottish Government whether it will provide an update on the total cost of any financial penalties issued by Transport Scotland to CalMac Ferries since October 2022.

The answer

Answered by Fiona Hyslop on 17 May 2024 · 10 days after it was lodged, on time

The level of performance deductions incurred by CalMac Ferries Ltd since October 2022 has been answered recently in a Freedom of Information request.
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. Details of the above Freedom of Information request can be found using the link: CalMac Ferries Limited performance deductions 2022/23
- 2023/24: FOI release
- gov.scot (www.gov.scot)
The level of penalties, as result of late submission of reporting, in respect of Contract Year 7 (October 2022 to September 2023) is £1,040,794

In the Official Report

No contribution in the Official Report cites S6W-27324 by reference.