Written Question · S6W-27312 · Session 6
How many new masts it anticipates will be deployed through the Scottish 4G Infill Programme (S4GI), broken down by local authority area.
The question
To ask the Scottish Government how many new masts it anticipates will be deployed through the Scottish 4G Infill Programme (S4GI), broken down by local authority area.
The answer
The Scottish 4G Infill (S4GI) Programme completed in November 2023 with the successful delivery of 55 new masts. No further masts will be deployed through the S4GI programme.
In the Official Report
No contribution in the Official Report cites S6W-27312 by reference.