Written Question · S6W-27028 · Session 6
Further to the answer to question S6W-26975 by Richard Lochhead on 24 April 2024, and in light of the UK Government’s publication, Project …
The question
To ask the Scottish Government, further to the answer to question S6W-26975 by Richard Lochhead on 24 April 2024, and in light of the UK Government’s publication, Project Gigabit progress update
- April 2024, whether it expects Project Gigabit procurement covering Fife to launch throughout 2024.
The answer
The Scottish Government and Building Digital UK (BDUK) have worked together to develop a number of potential Type A (local) and Type B (regional) Project Gigabit procurements in Scotland. The Scottish Government will lead delivery of these procurements, so that Project Gigabit and our own Reaching 100% (R100) programme can work together in Scotland.
A potential procurement in the Fife, Perth and Kinross areas has been identified as part of this process. It is expected that this procurement will launch later in 2024, so long as the Scottish Government is confident that there is the continued supplier interest necessary for it to succeed.
A potential procurement in the Fife, Perth and Kinross areas has been identified as part of this process. It is expected that this procurement will launch later in 2024, so long as the Scottish Government is confident that there is the continued supplier interest necessary for it to succeed.
In the Official Report
No contribution in the Official Report cites S6W-27028 by reference.