Written Question · S6W-26978 · Session 6
How much of the £60 million National Acquisition Programme funding had been spent by the end of the 2023-24 financial year, and how many so…
The question
To ask the Scottish Government how much of the £60 million National Acquisition Programme funding had been spent by the end of the 2023-24 financial year, and how many social homes this funding delivered, broken down by local authority area.
The answer
In 2023-2024 a total of £83.146 million was spent and a total of 1,498 affordable homes were delivered through the National Acquisition Programme (NAP). The following table provides a breakdown of these figures by local authority area.
Due to the nature of the Affordable Housing Supply Programme (AHSP), projects may draw down grant across multiple financial years. Spend, therefore, does not necessarily directly correlate to the number of homes delivered in the same financial year, as homes are only recorded as complete once a project record has fully completed.Local Authority Area Spend (£m) Homes Delivered Aberdeen City 4.234 126 Aberdeenshire 1.131 16 Angus 1.846 26 Argyll & Bute 0.182 0 City of Edinburgh 9.027 138 Clackmannanshire 1.974 57 Dumfries & Galloway 0.035 1 Dundee City 0.520 13 East Ayrshire 0.925 30 East Dunbartonshire 2.96421East Lothian 0.18634East Renfrewshire 0.2486Falkirk 3.15070Fife 2.97057Glasgow City 17.069176Inverclyde 0.53733Midlothian 0.19538Moray 0.042 1 North Ayrshire 2.417 7 North Lanarkshire 7.972 110 Perth & Kinross 2.497 59 Renfrewshire 0.897 27 Scottish Borders 1.450 22 Shetland Islands 0.228 3 South Ayrshire 1.455 37 South Lanarkshire 9.723 202 Stirling 1.450 37 The Highland Council 3.932 65 West Dunbartonshire 3.890 41 West Lothian 0.000 45 Total 83.146 1,498
Of the £83.146 million spent a total of £9.587 million was spent on projects to be initially used by Ukrainian displaced persons and later returned to be used within the wider social housing supply after a period of up to 3 years.
Due to the nature of the Affordable Housing Supply Programme (AHSP), projects may draw down grant across multiple financial years. Spend, therefore, does not necessarily directly correlate to the number of homes delivered in the same financial year, as homes are only recorded as complete once a project record has fully completed.Local Authority Area Spend (£m) Homes Delivered Aberdeen City 4.234 126 Aberdeenshire 1.131 16 Angus 1.846 26 Argyll & Bute 0.182 0 City of Edinburgh 9.027 138 Clackmannanshire 1.974 57 Dumfries & Galloway 0.035 1 Dundee City 0.520 13 East Ayrshire 0.925 30 East Dunbartonshire 2.96421East Lothian 0.18634East Renfrewshire 0.2486Falkirk 3.15070Fife 2.97057Glasgow City 17.069176Inverclyde 0.53733Midlothian 0.19538Moray 0.042 1 North Ayrshire 2.417 7 North Lanarkshire 7.972 110 Perth & Kinross 2.497 59 Renfrewshire 0.897 27 Scottish Borders 1.450 22 Shetland Islands 0.228 3 South Ayrshire 1.455 37 South Lanarkshire 9.723 202 Stirling 1.450 37 The Highland Council 3.932 65 West Dunbartonshire 3.890 41 West Lothian 0.000 45 Total 83.146 1,498
Of the £83.146 million spent a total of £9.587 million was spent on projects to be initially used by Ukrainian displaced persons and later returned to be used within the wider social housing supply after a period of up to 3 years.