Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-26795 · Session 6

Further to the answer to question S6W-26225 by Fiona Hyslop on 8 April 2024, what the estimated capital expenditure on the M8 Woodside Viad…

Answered Asked by Paul Sweeney Lab Lodged 8 Apr 2024

The question

To ask the Scottish Government, further to the answer to question S6W-26225 by Fiona Hyslop on 8 April 2024, what the estimated capital expenditure on the M8 Woodside Viaduct project is expected to be during the 2024-25 financial year.

The answer

Answered by Fiona Hyslop on 25 Apr 2024 · 17 days after it was lodged, on time

The M8 Woodside Viaducts are a vital element of the motorway and road network serving Glasgow, the wider region and country, carrying approximately 150,000 vehicles per day. The structure requires to be temporarily propped to facilitate the refurbishment of the bridge elements in need of repair. The temporary propping design and implementation is highly complex in nature and requires careful consideration of the underground services and other site constraints in the vicinity of the Viaducts.
The budget allocation for the ongoing works on the Woodside Viaduct project for the 2024-25 financial year is £46.97m.

In the Official Report

No contribution in the Official Report cites S6W-26795 by reference.