How much of the £500 million, which was originally allocated to the Bus Partnership Fund, has been spent.

Answered Asked by Rachael Hamilton Con Lodged 8 Apr 2024

The question

To ask the Scottish Government how much of the £500 million, which was originally allocated to the Bus Partnership Fund, has been spent.

The answer

Answered by Jim Fairlie on 29 Apr 2024 · 21 days after it was lodged, on time

We have awarded £26.9 million in funding for bus priority through the Bus Partnership Fund, with £20.5 million expected to be spent by 31 March 2024. However that figure will need to be confirmed following the processing of final claims from Partnerships
- consisting of local authorities, bus operators and other key stakeholders – in the coming months.
The awards made through the Bus Partnership Fund to date were the first step towards delivering long term investment in bus priority infrastructure, beyond the course of the parliament.
Following the United Kingdom autumn statement delivering the worst-case scenario for Scotland and a nearly 9 per cent real-terms cut in our capital budget from the UK Government, the Scottish Government had to take difficult decisions to deliver a balanced and sustainable spending plan for 2024-25. As such, regrettably, the Bus Partnership Fund has been paused for 2024-25. However, future funding availability will be considered as part of our annual budget-setting process and prioritisation exercises.

In the Official Report

No contribution in the Official Report cites S6W-26769 by reference.