Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S6W-26336 · Session 6

 further to the answer to question S6W-08117 by Jenny Gilruth on 6 May 2022, whether all of the deliverables of the rail improvement projec…

Answered Asked by Liam Kerr Con Lodged 19 Mar 2024

The question

To ask the Scottish Government, further to the answer to question S6W-08117 by Jenny Gilruth on 6 May 2022, whether all of the deliverables of the rail improvement project are expected to be completed by the end of 2026, and what has been achieved by the project since the previous question was answered in May 2022.

The answer

Answered by Fiona Hyslop on 11 Apr 2024 · 23 days after it was lodged, on time

Given the extremely challenging financial climate, due to UK Government capital budget cuts, we need to consider the time over which the project can be completed. I have asked that a review is undertaken and will ensure that an update is provided to the Parliament in due course.
Regarding what has been achieved by the project, I refer the Member to the answers to S6W-25277 on 1 March 2024 and S6W-24106 on 30 January 2024 .
All answers to written Parliamentary Questions are available on the Parliament's website:, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers

In the Official Report

No contribution in the Official Report cites S6W-26336 by reference.