Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S6W-26177 · Session 6

What assessment it has made of the connections between Peterhead Power Station and the Scottish Cluster in relation to enabling carbon capt…

Answered Asked by Monica Lennon Lab Lodged 13 Mar 2024

The question

To ask the Scottish Government what assessment it has made of the connections between Peterhead Power Station and the Scottish Cluster in relation to enabling carbon capture.

The answer

Answered by Gillian Martin on 21 Mar 2024 · 8 days after it was lodged, on time

It is proposed that the carbon capture project at Peterhead Power Station would connect into the CCS infrastructure being developed by the Acorn Project and the wider Scottish Cluster. This would see its emissions transported through shared pipelines and safely stored under the North Sea.

In the Official Report

No contribution in the Official Report cites S6W-26177 by reference.