What assessment it has made of any potential public expenditure or contingent liability implications for its Budget to de-risk or otherwise…

Answered Asked by Rhoda Grant Lab Lodged 1 Mar 2024

The question

To ask the Scottish Government what assessment it has made of any potential public expenditure or contingent liability implications for its Budget to de-risk or otherwise sufficiently underwrite private investment in nature sufficient to deliver private investment at the scale of (a) £5 billion, (b) £10 billion and (c) £15 billion up to 2032, in the absence of carbon prices capable of fully funding private investment ambitions, and whether it will publish any such assessment.

The answer

Answered by Mairi McAllan on 13 Mar 2024 · 12 days after it was lodged, on time

Options are currently being explored for spending models on nature restoration that can encourage greater responsible private investment while maximising the value of public spending. This includes consideration of ‘blended finance’ mechanisms where public funding is used in a more targeted way to support increased nature restoration activity by attracting responsible private investment.
The Scottish Government has not assessed potential public expenditure or contingent liability implications for its budget to de-risk or otherwise sufficiently underwrite private investment in nature. Budget implications would be published in line with usual processes.

In the Official Report