Further to the answer to question S6W-20147 by Fiona Hyslop on 10 August 2023, whether it can provide an update on Springburn railway stati…

Answered Asked by Paul Sweeney Lab Lodged 6 Feb 2024

The question

To ask the Scottish Government, further to the answer to question S6W-20147 by Fiona Hyslop on 10 August 2023, whether it can provide an update on Springburn railway station being nominated for Access for All scheme funding for Control Period 7 (2024-2029).

The answer

Answered by Fiona Hyslop on 22 Feb 2024 · 16 days after it was lodged, on time

As the member is aware The Access for All scheme is a UK Government scheme and as such is managed by the UK Department for Transport (DfT).
It is anticipated the Department for Transport will announce which stations will be prioritised for funding through the Access for All Scheme in the course of this year.

In the Official Report

No contribution in the Official Report cites S6W-25308 by reference.