Written Question · S6W-24718 · Session 6
Further to the answer to question S6W-24477 by Joe FitzPatrick on 18 January 2024, what its position is on whether the year-long timescale …
The question
To ask the Scottish Government, further to the answer to question S6W-24477 by Joe FitzPatrick on 18 January 2024, what its position is on whether the year-long timescale to review this planning application is acceptable, and what impact determination periods of this length have on the efficiency of (a) urban development, (b) investment and (c) economic growth in Glasgow, relative to peer cities.
The answer
Scottish Ministers intervene in only a handful of cases each year and generally only where they raise issues of national importance. These can sometimes be among the more complex planning cases which require careful consideration. Nevertheless, it is always our aim to progress cases to a decision as quickly as possible, recognising the vital role planning and the development sector play in investing and shaping our places and communities and the impact on this of unnecessary delays.
In this instance, whilst the application was called in by Ministers on 27 February 2023, it was not until mid-June 2023 that the reporter received all the relevant application information from Glasgow City Council to allow arrangements to be made to start the examination of these proposals. This information included representations from over 150 members of the public. The reporter held a hearing in September 2023 and parties final submissions were received in December 2023.
The reporter has now submitted the report and recommendation to Ministers, who will make the final decision as to whether or not planning permission should be granted for this proposed development.
In this instance, whilst the application was called in by Ministers on 27 February 2023, it was not until mid-June 2023 that the reporter received all the relevant application information from Glasgow City Council to allow arrangements to be made to start the examination of these proposals. This information included representations from over 150 members of the public. The reporter held a hearing in September 2023 and parties final submissions were received in December 2023.
The reporter has now submitted the report and recommendation to Ministers, who will make the final decision as to whether or not planning permission should be granted for this proposed development.