Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-24374 · Session 6

What action it plans to take to bring the Ferrymuir Gait access issue to a final conclusion.

Answered Asked by Foysol Choudhury Lab Lodged 8 Jan 2024

The question

To ask the Scottish Government what action it plans to take to bring the Ferrymuir Gait access issue to a final conclusion.

The answer

Answered by Fiona Hyslop on 19 Jan 2024 · 11 days after it was lodged, on time

Transport Scotland remains in positive dialogue with Ambassador Living (the developer for Forthview Housing Development) to reach an agreement on the use of Ferrymuir Gait as an access. This is following a legal process in order to finalise matters, which we hope to conclude in Spring 2024.

In the Official Report

No contribution in the Official Report cites S6W-24374 by reference.