Written Question · S6W-24106 · Session 6
How much of the £200 million that it committed to improve rail journey times between Aberdeen and the Central Belt by 2026 has been spent t…
The question
To ask the Scottish Government how much of the £200 million that it committed to improve rail journey times between Aberdeen and the Central Belt by 2026 has been spent to date.
The answer
Over the next five-year investment period, the Scottish Government has committed to invest £4.2 billion in the Scottish rail infrastructure in line with our High-Level Output Specification.
The total invested to 9th December 2023 on projects to reduce journey times between Aberdeen and the Central Belt by 2026 is £15.5m. Of this figure, £8.7m has been spent on the Aberdeen – Central Belt Journey Time Improvement project, and £6.8m has been spent on the project to improve rail line speeds in the Barnhill area between Perth and Dundee. The investment at Barnhill remodelled a junction between the Tay Viaduct at Perth and Barnhill to increase line speeds over it from 20mph to 50mph. It is a direct enabler for the plan to reduce rail journey times between the Central Belt and the North-East, improving connectivity and enhancing capacity for both passenger and freight trains on the route.
The Scottish Government is continuing to develop the business case for Aberdeen to Central Belt rail enhancements. This will be considered in in the coming months and within the context of the funding available for rail enhancements next year. We remain firmly committed to infrastructure investment as a key factor in securing economic growth and high-quality public infrastructure across Scotland, including spending over £1.6 billion in 2024-25 to operate, maintain and improve Scotland’s railway.
The total invested to 9th December 2023 on projects to reduce journey times between Aberdeen and the Central Belt by 2026 is £15.5m. Of this figure, £8.7m has been spent on the Aberdeen – Central Belt Journey Time Improvement project, and £6.8m has been spent on the project to improve rail line speeds in the Barnhill area between Perth and Dundee. The investment at Barnhill remodelled a junction between the Tay Viaduct at Perth and Barnhill to increase line speeds over it from 20mph to 50mph. It is a direct enabler for the plan to reduce rail journey times between the Central Belt and the North-East, improving connectivity and enhancing capacity for both passenger and freight trains on the route.
The Scottish Government is continuing to develop the business case for Aberdeen to Central Belt rail enhancements. This will be considered in in the coming months and within the context of the funding available for rail enhancements next year. We remain firmly committed to infrastructure investment as a key factor in securing economic growth and high-quality public infrastructure across Scotland, including spending over £1.6 billion in 2024-25 to operate, maintain and improve Scotland’s railway.
In the Official Report
No contribution in the Official Report cites S6W-24106 by reference.