Whether it will provide an update on Transport Scotland’s £4 million contract with Turner and Townsend for project and programme management…

Answered Asked by Alex Rowley Lab Lodged 13 Sep 2023

The question

To ask the Scottish Government whether it will provide an update on Transport Scotland’s £4 million contract with Turner and Townsend for project and programme management support for the CHFS3 project.

The answer

Answered by Fiona Hyslop on 29 Sep 2023 · 16 days after it was lodged, on time

Transport Scotland are working with support from external specialist commercial and technical advisors Turner and Townsend, to progress development of the next CHFS contract. Work is underway to the develop the next CHFS3 contract including stakeholder engagement to support this process.

In the Official Report