What penalties are imposed on Openreach when delivery dates of the R100 programme are not met.

Answered Asked by Alexander Burnett Con Lodged 28 Aug 2023

The question

To ask the Scottish Government what penalties are imposed on Openreach when delivery dates of the R100 programme are not met.

The answer

Answered by Richard Lochhead on 19 Sep 2023 · 22 days after it was lodged, on time

Penalty clauses are not enforceable in Scots law and, as such, there are no penalties included in the R100 Contracts.