By what date it expects that the R100 superfast broadband programme will be completed.

Answered Asked by Murdo Fraser Con Lodged 20 Jun 2023

The question

To ask the Scottish Government by what date it expects that the R100 superfast broadband programme will be completed.

The answer

Answered by Richard Lochhead on 3 Jul 2023 · 13 days after it was lodged, on time

The R100 programme is expected to be completed by March 2028 when the final connections in the R100 North contract are delivered.
Around 99% of the connections being delivered through the R100 contracts are full-fibre, capable of delivering speeds of 1,000 Megabits per second (Mbps) – more than 30 times faster than our original superfast commitment.

In the Official Report

No contribution in the Official Report cites S6W-19328 by reference.