Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S6W-18217 · Session 6

Whether it will provide an update on the upgrading of a number of laybys on the A77.

Answered Asked by Sharon Dowey Con Lodged 18 May 2023

The question

To ask the Scottish Government whether it will provide an update on the upgrading of a number of laybys on the A77.

The answer

Answered by Kevin Stewart on 30 May 2023 · 12 days after it was lodged, on time

Investigation work has been undertaken on the upgrade of 4 laybys on the A77 between Ayr and Stranraer. The designs to improve these 4 laybys will be completed by the end of this calendar year with construction anticipated early in financial year 2024/25.

In the Official Report

No contribution in the Official Report cites S6W-18217 by reference.