Written Question · S6W-17986 · Session 6
In light of reports that the Minister for Transport has confirmed that Amey has carried out repairs to potholes on the A90 between Fraserbu…
The question
To ask the Scottish Government, in light of reports that the Minister for Transport has confirmed that Amey has carried out repairs to potholes on the A90 between Fraserburgh and Peterhead and that the operating company is currently programming permanent repairs, when it expects (a) Amey to have concluded the programming of permanent repairs and (b) the permanent repairs to have been completed.
The answer
As part of the ongoing management and maintenance of the A90 trunk road, Amey Ltd (Transport Scotland’s operating company for the North East area of Scotland) prepares and delivers a 1-year programme of works, based upon the findings from their continual inspections of the network. These can include larger carriageway resurfacing schemes, more localised patching works or individual pothole patch repairs.
This 1-year programme is agreed with Transport Scotland before the start of the financial year and as with all programmes of this nature, remains under review depending on the findings of subsequent inspections and any reprioritisation.
In terms of resurfacing works on the A90, schemes at Crimond, South of Crimond and South of St Fergus were completed during the last financial year (2022-23). These schemes provided an investment of £1.2 million on the A90 between Peterhead and Fraserburgh.
Additionally, Amey has programmed the following patching schemes for delivery in 2023-24 in the A90 Fraserburgh to Peterhead area.
Route
Location
Brief Description of project
Construction Start Date
Construction End Date
Value
A90
Berryslacks
Machine Patching
01-08-2023
30-08-2023
£30,000
A90
South of Leask
Machine Patching
01-08-2023
30-08-2023
£30,000
A90
Lunderton Layby to St Fergus Cemetery
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
South of St Fergus
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
Logie Lodges to B9033
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
Cortes Village
Machine Patching
01-11-2023
30-11-2023
£30,000
A90
Philorth
Machine Inlay Patching
01-11-2023
30-11-2023
£60,000
As noted in our recent correspondence, my reply of 20 April referred to thirty Category 1 defects between Fraserburgh and Peterhead, which Amey had temporarily repaired to make safe. Since then, 9 of these were permanently repaired within the following 28 days. For the remaining defects, engineers have reviewed and determined that, on this occasion it is more effective to undertake more substantial patching at these locations. Given the proximity and nature of these locations, this approach will capture a wider area of repair than singular repairs, adding longevity but with less disruption to the travelling public.
This 1-year programme is agreed with Transport Scotland before the start of the financial year and as with all programmes of this nature, remains under review depending on the findings of subsequent inspections and any reprioritisation.
In terms of resurfacing works on the A90, schemes at Crimond, South of Crimond and South of St Fergus were completed during the last financial year (2022-23). These schemes provided an investment of £1.2 million on the A90 between Peterhead and Fraserburgh.
Additionally, Amey has programmed the following patching schemes for delivery in 2023-24 in the A90 Fraserburgh to Peterhead area.
Route
Location
Brief Description of project
Construction Start Date
Construction End Date
Value
A90
Berryslacks
Machine Patching
01-08-2023
30-08-2023
£30,000
A90
South of Leask
Machine Patching
01-08-2023
30-08-2023
£30,000
A90
Lunderton Layby to St Fergus Cemetery
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
South of St Fergus
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
Logie Lodges to B9033
Machine Inlay Patching
01-09-2023
30-09-2023
£150,000
A90
Cortes Village
Machine Patching
01-11-2023
30-11-2023
£30,000
A90
Philorth
Machine Inlay Patching
01-11-2023
30-11-2023
£60,000
As noted in our recent correspondence, my reply of 20 April referred to thirty Category 1 defects between Fraserburgh and Peterhead, which Amey had temporarily repaired to make safe. Since then, 9 of these were permanently repaired within the following 28 days. For the remaining defects, engineers have reviewed and determined that, on this occasion it is more effective to undertake more substantial patching at these locations. Given the proximity and nature of these locations, this approach will capture a wider area of repair than singular repairs, adding longevity but with less disruption to the travelling public.