Written Question · S6W-17345 · Session 6
Whether it will provide an update on progress on the construction of a new grade-separated junction on the A720 at Sheriffhall.
The question
To ask the Scottish Government whether it will provide an update on progress on the construction of a new grade-separated junction on the A720 at Sheriffhall.
The answer
The Scottish Government is committed to delivering the grade separation of Sheriffhall roundabout, as part of its £300 million commitment to the Edinburgh and South East Scotland City Region Deal.
Following publication of the draft Orders and Environmental Statement, Transport Scotland received a significant number of objections to the proposed scheme. Although Transport Scotland engaged widely with objectors, it was unable to resolve all objections. In view of this, a Public Local Inquiry was held from 31 January to 8 February 2023. As with all trunk road projects this is the appropriate statutory forum for considering objections received and not withdrawn. The independent Reporter is now giving detailed consideration to all evidence before making recommendations to the Scottish Ministers for a decision.
Construction of the proposed scheme can only commence if it is approved under the relevant statutory authorisation process and thereafter a timetable for its progress can be set.
Following publication of the draft Orders and Environmental Statement, Transport Scotland received a significant number of objections to the proposed scheme. Although Transport Scotland engaged widely with objectors, it was unable to resolve all objections. In view of this, a Public Local Inquiry was held from 31 January to 8 February 2023. As with all trunk road projects this is the appropriate statutory forum for considering objections received and not withdrawn. The independent Reporter is now giving detailed consideration to all evidence before making recommendations to the Scottish Ministers for a decision.
Construction of the proposed scheme can only commence if it is approved under the relevant statutory authorisation process and thereafter a timetable for its progress can be set.
In the Official Report
No contribution in the Official Report cites S6W-17345 by reference.