Further to the answer to question S6W-16277 by Kevin Stewart on 6 April 2023, which states that “Transport Scotland intends to achieve jour…

Answered Asked by Liam Kerr Con Lodged 7 Apr 2023

The question

To ask the Scottish Government, further to the answer to question S6W-16277 by Kevin Stewart on 6 April 2023, which states that “Transport Scotland intends to achieve journey time savings via a series of infrastructure upgrades including signal enhancements and specific capacity alterations to facilitate the operation of more and faster trains”, what the (a) nature, (b) geographical location and (c) potential time-saving of each infrastructure upgrade is, and how it plans to reduce the ScotRail journey time between (i) Aberdeen and Dundee by three minutes and (ii) Dundee and Edinburgh by 17 minutes, by 2026.

The answer

Answered by Kevin Stewart on 9 May 2023 · 32 days after it was lodged, on time

As set out in my response to PQ S6W-16276 on 6 April 2023, Transport Scotland intend to publish the Outline Business Case for the Aberdeen to Central Belt Rail Enhancement Project later in the year. This will provide the requested details of the specific infrastructure upgrades and their contributions to journey time savings.
In the meantime, Transport Scotland has been updating key stakeholders on the progress of the design of this project.