Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S6W-16204 · Session 6

Further to the answer to question S5W-31530 by Roseanna Cunningham on 14 September 2020, whether it will provide an updated table of capaci…

Answered Asked by Maurice Golden Con Lodged 24 Mar 2023

The question

To ask the Scottish Government, further to the answer to question S5W-31530 by Roseanna Cunningham on 14 September 2020, whether it will provide an updated table of capacity figures to 2023, with projections to 2030.

The answer

Answered by Lorna Slater on 24 Apr 2023 · 31 days after it was lodged, on time

The following table shows permitted incineration capacity figures held by SEPA to 2023.
The first report of the independent review of the role of incineration in Scotland’s waste hierarchy, made assumptions about capacity beyond 2023, although in doing so, noted that it is unlikely that all facilities in the pipeline (i.e. those not build and at various stages of planning and permitting) will be built. The first report from the independent review is available here: Stop, Sort, Burn, Bury (www.gov.scot)
Year
Total operational waste incineration operational capacity (million tonnes)
Operational biomass incineration capacity (million tonnes)
Operational municipal waste incineration capacity (million tonnes)
Permitted municipal waste incineration capacity (million tonnes)
2007
1.1
0.9
0.2
0.2
2008
1.1
0.9
0.2
0.2
2009
1.1
0.9
0.2
0.2
2010
1.1
0.9
0.2
0.2
2011
1.1
0.9
0.2
0.5
2012
1.6
1.4
0.2
0.5
2013
1.6
1.4
0.2
0.5
2014
1.6
1.4
0.2
0.6
2015
1.6
1.4
0.2
0.5
2016
1.6
1.4
0.2
0.7
2017
1.6
1.4
0.2
0.7
2018
1.6
1.4
0.2
0.9
2019
2.4
1.4
1
1.3
2020
2.4
1.4
1
1.5
2021
2.5
1.4
1.1
2.1
2022
2.5
1.4
1.1
2.2
2023
2.9
1.4
1.5
2.2

In the Official Report

No contribution in the Official Report cites S6W-16204 by reference.