What measures Transport Scotland has in place to monitor the success rates of the tree planting that it carried out along the Aberdeen West…
The question
To ask the Scottish Government what measures Transport Scotland has in place to monitor the success rates of the tree planting that it carried out along the Aberdeen Western Peripheral Route.
The answer
The Aberdeen Western Peripheral Road/Balmedie-Tipperty (AWPR/B-T) section of the A90 is managed on behalf of Scottish Ministers/Transport Scotland by the Design Build Finance and Operate (DBFO) company Aberdeen Roads Limited (ARL). The associated landscaping areas are included in the Agreement with ARL. Around 1.5 million trees were planted. The project is in year 4 of the 5 year Establishment Period. As the name suggests the Establishment Period is designed to closely monitor plant development and take action if appropriate to address tree plant establishment failures.
During the Establishment Period ARL’s appointed specialist landscape architect is required to undertake inspections of the tree planting 6 times in year one, 4 times in year 2, and 3 times for each of years 3, 4 and 5. On completion of the Establishment Period the landscaping enters the Operation and Maintenance (O&M) phase when annual inspections are required. The O&M period ends in 2047.
Following each inspection the landscape architect makes recommendations which are carried out by ARL and which could include tree tube/guard removal as the trees develop as well as identifying opportunities to enhance biodiversity and reduce pesticide application. Other work carried out over the last 4 to 5 years includes weed control, grass cutting in amongst those trees, pruning of damaged branches and re-staking of trees.
The appointed Contracting Authority (Jacobs consultants) receive annual reports and undertake joint inspections to ensure the contractual requirements are being fulfilled. Jacobs subsequently advise Transport Scotland of progress and discuss any matters as necessary.
During the Establishment Period ARL’s appointed specialist landscape architect is required to undertake inspections of the tree planting 6 times in year one, 4 times in year 2, and 3 times for each of years 3, 4 and 5. On completion of the Establishment Period the landscaping enters the Operation and Maintenance (O&M) phase when annual inspections are required. The O&M period ends in 2047.
Following each inspection the landscape architect makes recommendations which are carried out by ARL and which could include tree tube/guard removal as the trees develop as well as identifying opportunities to enhance biodiversity and reduce pesticide application. Other work carried out over the last 4 to 5 years includes weed control, grass cutting in amongst those trees, pruning of damaged branches and re-staking of trees.
The appointed Contracting Authority (Jacobs consultants) receive annual reports and undertake joint inspections to ensure the contractual requirements are being fulfilled. Jacobs subsequently advise Transport Scotland of progress and discuss any matters as necessary.