Written Question · S6W-15922 · Session 6
Further to the answer to question S6W-10628 by Ivan McKee on 6 September 2022, whether it will provide an update on when it anticipates the…
The question
To ask the Scottish Government, further to the answer to question S6W-10628 by Ivan McKee on 6 September 2022, whether it will provide an update on when it anticipates the 4G masts in Rackwick and Stronsay in Orkney, as part of the Scottish 4G Infill Programme, will be activated.
The answer
We can confirm that build work for the Scottish 4G Infill programme masts at both Rackwick and Stronsay is now complete and activation is currently expected to take place in April 2023.
In the Official Report
No contribution in the Official Report cites S6W-15922 by reference.