The question

To ask the Scottish Government on what date it (a) received the request from NHS Lanarkshire and (b) confirmed the 2022-23 funding for the National Treatment Centre in Cumbernauld.

The answer

Answered by Humza Yousaf on 16 Mar 2023 · 14 days after it was lodged, on time

On 24 February 2023 NHS Lanarkshire informed Scottish Government that they required funding of £193k to support their National Treatment Centre and this funding will be provided as it is an agreed national priority.

In the Official Report