Written Question · S6W-14856 · Session 6

Whether it is the case that only two of its buildings have a heat pump installed; what action it will take to increase the number of its bu…

Answered Asked by Monica Lennon Lab Lodged 6 Feb 2023

The question

To ask the Scottish Government whether it is the case that only two of its buildings have a heat pump installed; what action it will take to increase the number of its buildings that have a heat pump installed, and within what timescale will any such action be undertaken.

The answer

Answered by Ivan McKee on 21 Feb 2023 · 15 days after it was lodged, on time

Currently 1 building on the core Scottish Government estate has a heat pump installed (Tweedbank)
Feasibility studied will be carried out in the first quarter of 2023/24 financial year to look at a range of renewable technologies for the estate, including air source heat pumps.
Timescale for installing air source heat pumps to suitable buildings:-2023-24 – (1st quarter)
- Feasibility studies will be carried out with business cases and funding applications submitted for suitable projects.2023-24 – (2nd quarter)
- Apply, design and install power cable upgrades if required or – if the incoming power needs to be increased from the supplier.2023-24 – (3rd/4th quarter quarter)
- Design, tender, appoint a contractor, planning permissions2024-25 – Installation of ASHP, radiators, pipework.