Further to the answer to question S6W-13230 by Lorna Slater on 20 December 2022, according to the modelling done by Zero Waste Scotland, ho…

Answered Asked by Brian Whittle Con Lodged 24 Jan 2023

The question

To ask the Scottish Government, further to the answer to question S6W-13230 by Lorna Slater on 20 December 2022, according to the modelling done by Zero Waste Scotland, how long on average after the initial investments would local authorities expect to experience a net financial benefit.

The answer

Answered by Lorna Slater on 7 Feb 2023 · 14 days after it was lodged, on time

The modelling followed the legislative timeframe of achieving 90% capture of single use drinks containers by 2025. The full benefits would be realised at that time. An indication at 80% performance was also provided to enable mapping of the scheme performance by local authority.

In the Official Report