Further to the answer to question S6W-12876 by Lorna Slater on 20 December 2022, how many of the projects funded through the Recycling Impr…

Answered Asked by Maurice Golden Con Lodged 23 Dec 2022

The question

To ask the Scottish Government, further to the answer to question S6W-12876 by Lorna Slater on 20 December 2022, how many of the projects funded through the Recycling Improvement Fund are being delivered wholly or in partnership with commercial partners, and how many applications for project funding were received from commercial partners in total.

The answer

Answered by Lorna Slater on 18 Jan 2023 · 26 days after it was lodged, on time

Currently, five funded projects are being delivered by local authorities in partnership with commercial partners, including third sector and/or for profit organisations:
• North Ayrshire
• Fife
• Aberdeen City (two projects)
• East Lothian
The funding programme is only open to local authorities and local authority-led partnerships, no applications were therefore received directly from commercial partners.

In the Official Report

No contribution in the Official Report cites S6W-13621 by reference.