Written Question · S6W-13023 · Session 6
Further to the answer to question S5W-20998 by Michael Matheson on 1 February 2019, what action it has taken to fulfil the commitment that …
The question
To ask the Scottish Government, further to the answer to question S5W-20998 by Michael Matheson on 1 February 2019, what action it has taken to fulfil the commitment that was made by the then First Minister in August 2008, following a Cabinet meeting in Inverness, to reduce train journey times between Inverness and Edinburgh to at least two hours 45 minutes, and an average of three hours, with the aim of making “railway travel to the heart of the Highlands, in terms of time, competitive with roads… by a mixture of projects, including line improvement, additional passing loops, double-tracking and signalling upgrades”; what improvements projects were introduced, broken down by what progress has been made with each, and, in light of the comment that “the timescale for implementation is 2011-12”, for what reason the target date was not met, and by what date this level of service will be operational.
The answer
The Scottish Government’s Infrastructure Investment Plan, published in 2011, stated that the Highland Main Line (HML) Rail Improvement project would be completed in phases between 2014 and 2025.
Phase one was delivered as planned in December 2012, increasing services from 9 to 11 trains per day in each direction, and reducing journey times by an average of 6 minutes at a cost of £1.2 million.
HML Phase Two was completed in March 2019 at a cost of £57m. This phase delivered signalling upgrades at Aviemore and Pitlochry stations, along with an extension of the passing loop at Aviemore and the reconfiguration and extension of the platforms at Pitlochry, enabling simultaneous arrival of trains at both these stations.
In line with a recommendation from the draft Strategic Transport Project Review 2, Network Rail is developing proposals for the lengthening of several passing loops along the line to enable longer and more frequent freight and passenger services. These proposals will then be considered by Transport Scotland, taking into account the usual affordability and value for money considerations.
Achieving freight modal shift from road to rail has been recognised as a key component in achieving carbon reductions within Scotland’s transport system. A single freight train can typically remove 76 HGVs from adjacent roads, reducing congestion and improving safety. The infrastructure work delivered already and an integrated approach to passenger and freight timetable patterns have created capacity for additional rail freight on the Highland Main Line and discussions with key rail freight customers are underway to use this capacity.
Phase one was delivered as planned in December 2012, increasing services from 9 to 11 trains per day in each direction, and reducing journey times by an average of 6 minutes at a cost of £1.2 million.
HML Phase Two was completed in March 2019 at a cost of £57m. This phase delivered signalling upgrades at Aviemore and Pitlochry stations, along with an extension of the passing loop at Aviemore and the reconfiguration and extension of the platforms at Pitlochry, enabling simultaneous arrival of trains at both these stations.
In line with a recommendation from the draft Strategic Transport Project Review 2, Network Rail is developing proposals for the lengthening of several passing loops along the line to enable longer and more frequent freight and passenger services. These proposals will then be considered by Transport Scotland, taking into account the usual affordability and value for money considerations.
Achieving freight modal shift from road to rail has been recognised as a key component in achieving carbon reductions within Scotland’s transport system. A single freight train can typically remove 76 HGVs from adjacent roads, reducing congestion and improving safety. The infrastructure work delivered already and an integrated approach to passenger and freight timetable patterns have created capacity for additional rail freight on the Highland Main Line and discussions with key rail freight customers are underway to use this capacity.