Written Question · S6W-12764 · Session 6
Further to the answer to question S6W-10463 by Shona Robison on 20 September 2022, how many proposed (a) homes and (b) projects included in…
The question
To ask the Scottish Government, further to the answer to question S6W-10463 by Shona Robison on 20 September 2022, how many proposed (a) homes and (b) projects included in affordable housing supply programme grant applications that it has received have been (i) below and (ii) above benchmark, also broken down by baseline benchmark type, in (A) August, (B) September, (C) October and (D) November 2022.
The answer
The following table shows number of homes and projects that have been submitted for approval in August, September, October and November 2022, broken down by baseline benchmark type and whether above, at, or below benchmark. To note that the table includes some projects still under active appraisal:
City and Urban
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
11
10
13
15
49
Total No. of Homes Submitted against Benchmark
226
226
321
502
1,275
No. of Projects Submitted ABOVE Benchmark
7
5
10
11
33
No. of Homes Submitted ABOVE
Benchmark
156
155
258
243
812
No. of Projects Submitted AT Benchmark
1
2
2
5
No. of Homes Submitted AT Benchmark
24
53
54
131
No. of Projects Submitted BELOW Benchmark
4
4
1
2
11
No. of Homes Submitted BELOW
Benchmark
70
47
10
205
332
Other Rural
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
1
4
1
3
9
Total No. of Homes Submitted against Benchmark
28
99
1
63
191
No. of Projects Submitted ABOVE
Benchmark
2
1
3
6
No. of Homes Submitted ABOVE
Benchmark
23
1
55
79
No. of Projects Submitted AT
Benchmark
1
1
2
No. of Homes Submitted AT
Benchmark
28
20
48
No. of Projects Submitted BELOW Benchmark
1
1
2
No. of Homes Submitted BELOW
Benchmark
56
8
64
West Highland, Island Authorities & Remote/ Rural Argyll
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
1
1
2
1
5
Total No. of Homes Submitted against Benchmark
4
4
12
14
34
No. of Projects Submitted ABOVE Benchmark
1
1
2
1
5
No. of Homes Submitted ABOVE Benchmark
4
4
12
14
34
No. of Projects Submitted AT
Benchmark
0
No. of Homes Submitted AT
Benchmark
0
No. of Projects Submitted BELOW Benchmark
0
No. of Homes Submitted BELOW Benchmark
0
City and Urban
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
11
10
13
15
49
Total No. of Homes Submitted against Benchmark
226
226
321
502
1,275
No. of Projects Submitted ABOVE Benchmark
7
5
10
11
33
No. of Homes Submitted ABOVE
Benchmark
156
155
258
243
812
No. of Projects Submitted AT Benchmark
1
2
2
5
No. of Homes Submitted AT Benchmark
24
53
54
131
No. of Projects Submitted BELOW Benchmark
4
4
1
2
11
No. of Homes Submitted BELOW
Benchmark
70
47
10
205
332
Other Rural
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
1
4
1
3
9
Total No. of Homes Submitted against Benchmark
28
99
1
63
191
No. of Projects Submitted ABOVE
Benchmark
2
1
3
6
No. of Homes Submitted ABOVE
Benchmark
23
1
55
79
No. of Projects Submitted AT
Benchmark
1
1
2
No. of Homes Submitted AT
Benchmark
28
20
48
No. of Projects Submitted BELOW Benchmark
1
1
2
No. of Homes Submitted BELOW
Benchmark
56
8
64
West Highland, Island Authorities & Remote/ Rural Argyll
Project/ Home details
August
September
October
November
Total
Total No. of Projects Submitted against Benchmark
1
1
2
1
5
Total No. of Homes Submitted against Benchmark
4
4
12
14
34
No. of Projects Submitted ABOVE Benchmark
1
1
2
1
5
No. of Homes Submitted ABOVE Benchmark
4
4
12
14
34
No. of Projects Submitted AT
Benchmark
0
No. of Homes Submitted AT
Benchmark
0
No. of Projects Submitted BELOW Benchmark
0
No. of Homes Submitted BELOW Benchmark
0
In the Official Report
No contribution in the Official Report cites S6W-12764 by reference.