Further to the answer to question S6T-00960 by Lorna Slater on 15 November 2022, whether the figure in the statement that Scotland has “ove…

Answered Asked by Willie Rennie LD Lodged 15 Nov 2022

The question

To ask the Scottish Government, further to the answer to question S6T-00960 by Lorna Slater on 15 November 2022, whether the figure in the statement that Scotland has “over 40GW of potential offshore wind developments already in the pipeline” includes (a) currently operational offshore wind developments and (b) potential Innovation and Targeted Oil and Gas (INTOG) offshore wind developments.

The answer

Answered by Michael Matheson on 5 Dec 2022 · 20 days after it was lodged, on time

The statement that Scotland has over 40GW of potential offshore wind developments in the pipeline, subject to planning and consenting decisions, and finding a route to market, does not include (a) currently operational offshore wind projects and does include (b) estimated capacity for potential Innovation and Targeted Oil and Gas Decarbonisation (INTOG) leasing round offshore wind developments.

In the Official Report

No contribution in the Official Report cites S6W-12335 by reference.