Further to the answer to question S6T-00960 by Lorna Slater on 15 November 2022, which potential offshore wind developments were included i…
The question
To ask the Scottish Government, further to the answer to question S6T-00960 by Lorna Slater on 15 November 2022, which potential offshore wind developments were included in the figure in the statement that Scotland has “over 40GW of potential offshore wind developments already in the pipeline”.
The answer
The offshore wind developments included in the estimate of 40GW of potential offshore wind developments in the pipeline, subject to planning and consenting decisions, and finding a route to market, included:
3.8 gigawatts of projects currently under construction or awaiting construction [1]SeagreenInch CapeMoray WestNeart na Gaoithe
4.2 gigawatts of projects with lease options [2] Berwick BankPentland Floating Offshore Wind Farm5.7 gigawatts of estimated capacity for targeted oil and gas decarbonisation projects under the INTOG leasing round [3]0.5 gigawatts of estimated capacity for Innovation projects under the INTOG leasing round [4]27.6 gigawatts from 20 ScotWind projects [5]
[1] Scottish Energy Statistics Hub
- Pipeline renewable capacity by planning stage
Scotland, 2022 Q2 ? Scottish Energy Statistics Hub (shinyapps.io)
[2] Marine Scotland – Marine Projects
Marine Projects | Marine Scotland Information
[3] Scottish Government, Sectoral marine plan – offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
Supporting documents
- Sectoral marine plan
- offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
- gov.scot (www.gov.scot)
[4] Scottish Government, Sectoral marine plan – offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
Supporting documents
- Sectoral marine plan
- offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
- gov.scot (www.gov.scot)
[5] Crown Estate Scotland, “ScotWind Awards with Project Partners November 2022” https://www.crownestatescotland.com/resources/documents/scotwind-awards-with-project-partners-november-2022
3.8 gigawatts of projects currently under construction or awaiting construction [1]SeagreenInch CapeMoray WestNeart na Gaoithe
4.2 gigawatts of projects with lease options [2] Berwick BankPentland Floating Offshore Wind Farm5.7 gigawatts of estimated capacity for targeted oil and gas decarbonisation projects under the INTOG leasing round [3]0.5 gigawatts of estimated capacity for Innovation projects under the INTOG leasing round [4]27.6 gigawatts from 20 ScotWind projects [5]
[1] Scottish Energy Statistics Hub
- Pipeline renewable capacity by planning stage
Scotland, 2022 Q2 ? Scottish Energy Statistics Hub (shinyapps.io)
[2] Marine Scotland – Marine Projects
Marine Projects | Marine Scotland Information
[3] Scottish Government, Sectoral marine plan – offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
Supporting documents
- Sectoral marine plan
- offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
- gov.scot (www.gov.scot)
[4] Scottish Government, Sectoral marine plan – offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
Supporting documents
- Sectoral marine plan
- offshore wind for innovation and targeted oil and gas decarbonisation: initial plan framework
- gov.scot (www.gov.scot)
[5] Crown Estate Scotland, “ScotWind Awards with Project Partners November 2022” https://www.crownestatescotland.com/resources/documents/scotwind-awards-with-project-partners-november-2022
In the Official Report
No contribution in the Official Report cites S6W-12334 by reference.