Further to the answer to question S6W-10191 by Shona Robison on 6 September 2022, how many of those buildings, which have applied under the…

Answered Asked by Mark Griffin Lab Lodged 12 Oct 2022

The question

To ask the Scottish Government further to the answer to question S6W-10191 by Shona Robison on 6 September 2022, how many of those buildings, which have applied under the grant-based scheme, have received (a) partial and (b) full funding.

The answer

Answered by Shona Robison on 3 Nov 2022 · 22 days after it was lodged, on time

We have made 18 payments so far to 15 buildings, with 10 currently under assessment with a partial payment and 5 with full payment and assessment having concluded. All buildings with cladding concerns have and will continue to be offered fully funded assessments.

In the Official Report

No contribution in the Official Report cites S6W-11540 by reference.