Whether it will provide an update on the situation at Tarbolton Moss Landfill Site; what plans it has to clean up the site, and what negoti…

Answered Asked by Sharon Dowey Con Lodged 21 Sep 2022

The question

To ask the Scottish Government whether it will provide an update on the situation at Tarbolton Moss Landfill Site; what plans it has to clean up the site, and what negotiations it is having with all relevant stakeholders.

The answer

Answered by Mairi McAllan on 5 Oct 2022 · 14 days after it was lodged, on time

With funding from the Scottish Government, SEPA has contracted an environmental consultant to manage the construction of a leachate management system at the former landfill site at Tarbolton Moss, to prevent the ongoing discharges of landfill leachate to neighbouring watercourses and make it possible for leachate disposal to the public sewerage system. The design phase is now complete.
SEPA continue to monitor ongoing environmental risks at the site and completed their latest survey in August 2022. This found no significant increasing trends associated with the migration of landfill gas or impact to groundwater from leachate.
My officials are working closely with our public partners to consider further actions for the long-term restoration of the site.

In the Official Report