Written Question · S6W-10663 · Session 6
Whether there are any plans to implement tactile paving in all train stations to help disabled passengers to travel safely using trains.
The question
To ask the Scottish Government whether there are any plans to implement tactile paving in all train stations to help disabled passengers to travel safely using trains.
The answer
I can confirm that, Network Rail Scotland, has developed a plan for installing platform edge tactile paving at all Scottish stations by the end of the current Rail Regulatory Control Period 6 (end of March 2024). The work is being completed over two phases. Phase 1 installed tactile paving at 18 high priority stations by the end of March 2022, phase 2 will address the remaining 148 stations.
In the Official Report
No contribution in the Official Report cites S6W-10663 by reference.